Inauguration of number of sub-stations at RSP
Rourkela, Nov 30: In order to provide power supply for the erection, commissioning and constant uninterrupted operation of the massive expansion projects of Rourkela Steel Plant (RSP), a number of electrical installations have been set up. The timely power supply from the three Load Block Sub-Stations namely LBSS-IV, LBSS-V and LBSS-VI to the New Coke Ovens battery– 6 Complex, New Blast Furnace– V, Ore Bedding and Blending Plant Phase-III and the New Sinter Complex, enabled the commissioning, stabilization and operations of these Units. Recently all the erection jobs and automation commissioning including Auto Bus Transfer and complete communication of all feeders to centralized Power Distribution SCADA were completed by the collective efforts of the Projects and Power Distribution departments of RSP. On 28th November, LBSS-IV 33/6.6 KV Sub-Station was inaugurated by AK Bihari, GM (Projects). This Sub-Station provides power to the New Coke Oven– 6 Complex including New...